Please answer the following questions, based on the information presented during Bill Raymond's Fundamentals of Project Management session. Be sure to include your name at the end of the quiz for credit.
*
1.
Of these well-known project management techniques, which is the first known, documented, approach to linking tasks to determine the end date for a project?
(Required.)
The critical path method (or CPM).
The harmonogram (or harmonograf).
The Gantt chart.
*
2.
Define issues and risks.
(Required.)
An issue is something that did not yet occur but could happen. A risk is something that did occur and requires immediate action.
Issues and risks are substantially the same.
An issue is something that did occur and requires immediate action. A risk is something that did not occur but could happen.
*
3.
What is the major difference between an agile project and a waterfall project.
(Required.)
The waterfall project clearly articulates all the steps required to complete a project. The agile project does not need absolute clarity before work can begin.
An agile project is only for software development, where waterfall works for any project.
Agile projects do not fit within a waterfall schedule and vice-versa.
*