Here is some information about our old building from the 2017 SCHOOL FACILITIES ASSESSMENT REPORT & MASTER PLANNING:

Ongoing Maintenance Costs -- if building is empty and not used
Current Annual costs:
Natural Gas Usage  $15,600
Electric Usage  $6,000
Insurance  $6,600
Other costs include safety inspections and some maintenance
Estimated annual cost = $28,000 to $35,000

Upgrade to meet current building codes and safety standards -- for future use of building
Structural assessment
Upgrade fire alarms
Abatement of all asbestos ($55,235)
Potential unanticipated repairs
Estimated cost = $7.96 million

Replacement Cost
If the district was to construct an exact duplicate of the old building:
Replacement Cost = $11.85 million

Demolition Cost = $163,000


Question Title

* 1. Please tell us your affiliation with North Powder Charter School:

Question Title

* 2. Given the passage of the 2017 School Bond and the completion of our new school facility, what do you think should happen with our old middle/high school building?

Question Title

* 3. If you are a taxpayer who voted in favor of the 2017 School Bond, would you have voted the same way if you knew the old middle/high school would continue to exist and cost taxpayers $28,000-$35,000 annually to maintain?

Question Title

* 4. Is there anything else you would like to share with us?

0 of 4 answered
 

T