* 1. When the dimensions of the dug canals for the new dam project were compared to the plan, a huge variance was revealed. Therefore, the project manager had to call for a meeting with the team to decide what to do next. In which of the following process groups does the project manager’s activity take part?

Question Title

* 2. After creating the network diagram, the project manager identified three critical paths. What should the project manager do next?

Question Title

* 3. After completing the creation of the scope statement, a project manager wanted to make sure that all of the project deliverables were identified and could be managed effectively. So, they opted for the _____________________ method to develop the WBS in order to capture all of the project’s details.

Question Title

* 4. During a project status meeting, the project manager updated the sponsor on the project performance by informing them that the SPI is 0.75 and the CPI is 1.05. What does this indicate?

Question Title

* 5. A project manager is managing a project that consists in implementing an accounting application for a pet store. During a project performance review meeting, they presented the following figures:

AC = $4,000, PV = $5,000, and EV = $5,500. What does that indicate about the project?

Question Title

* 6. Network diagrams are a visual display of project work as they show the connection between work activities and how they progress from the project's start to its completion. The longest path in a network diagram is known as

Question Title

* 7. A project manager is assigned to a 12-month project that has a $100,000 budget. Six months have passed and $60,000 has been spent. On closer inspection, the project manager finds out that so far, only 40% of the work has been completed. The value of the completed 40% work is referred to as:

Question Title

* 8. In a predictive approach, which of the following statements are true about project deliverables? (Select two)

Question Title

* 9. Which of the following options represents the characteristics of the predictive project management approach? (Select two)

Question Title

* 10. Within the predictive approach, which of the following terms is used for both costs and schedules to establish what you’ll measure against later in the monitoring and controlling phase?

Question Title

* 11. The following diagram represents the decomposition of the project deliverables into smaller tasks. What is this diagram called?

Question Title

* 12. Prior to a meeting with the sponsor to update them on the project status, a project manager is going through the project status report which shows that the SPI is 0.8, while the CPI is 1.1. What should be more concerning to the project manager?

Question Title

* 13. A project manager is managing a project with a distributed team, fixed budget, and tight deadlines. Knowing that they’re adopting a predictive approach, what should the project manager do to avoid any scope creep and keep their team focused on delivering a product that meets requirements?

Question Title

* 14. A project manager is leading a high-risk project that has recently suffered from fluctuating performance and a high defect rate. During a meeting, the sponsor asks for an overview of work performance and where the project is currently standing. Which of the following documents should the project manager send to the sponsor?

Question Title

* 15. Before taking a long leave, a project manager informed the person filling in for them that they should regularly calculate the project’s Earned Value (EV). Among the following options, what is the right description of an Earned Value?