Question Title

* 1. The project sponsor informed the project manager that they have doubts about whether the resulting product will satisfy business demands. Therefore, they are looking to keep costs to a minimum. What should the project manager do?

Question Title

* 2. A project manager is examining the investment efficiency of two potential projects. Knowing that the discount rate is unknown, what should the project manager do?

Question Title

* 3. An organization is deliberating over two potential projects that have exactly the same payback period. After doing a benefit measurement analysis, the project manager finds out that project A has a lower Internal Rate of Return (IRR) than project B. What project should the organization choose? 

Question Title

* 4. A project manager receives a document from the customer containing the new project’s requirements. When going through the document, the project manager finds it difficult to understand certain requirements, outputs, and most importantly, the project’s ultimate goal. What should the project manager do next?

Question Title

* 5. To guide the development team on what they intend to achieve, a product owner of an HR solution shares the following table depicting the key deliverables of each quarter of the 9-month project. What agile artifact does this table represent?

                                        
Q1 2021Q2 2021Q3 2021
Web App
User management
Payroll module
Android App
Reporting module
Dashboard
iOS App
Leaves module

Question Title

* 6. The role of the product owner in an Agile project is:

Question Title

* 7. The team of a predictive project discovers that many implemented features are different from the outlined scope in the scope statement. Which of the following documents should the project manager refer to in order to deal with this matter?

Question Title

* 8. A project manager is facing some struggles after joining a new company; her superiors noticed that during a kick-off meeting, she had difficulty answering questions about how the project fits in with the organization’s objectives. What critical skill is the project manager lacking?

Question Title

* 9. A project manager is leading a project that has become so large (multiple teams, long duration, and huge budget) that the sponsor has been replaced by a steering committee. What should the project manager do to accommodate this new change?

Question Title

* 10. An organization assigned a new project manager to replace the one who recently left. What should the new project manager do first?

Question Title

* 11. A project manager is assigned to manage a software development project. When they came across one of the project's key stakeholders in the company’s hallway, the project manager seized the opportunity to get their feedback. The key stakeholder was impressed with the project’s progress and requested that the project manager urgently add a new user story for marketing the product. How should the project manager respond to this request?

Question Title

* 12. All stakeholders are in a meeting to discuss a new project that is expected to start within one month and to last at least 10 iterations. One of the stakeholders mentions that someone should take the responsibility of developing and maintaining the product roadmap. Who should take this responsibility? 

Question Title

* 13. A project manager is assigned to a hotel interior design project. One month into the project, the sponsor contacts the project manager to express his dissatisfaction with the deliverables, claiming that they match neither his requirements nor his expectations. How should the project manager react?

Question Title

* 14. A project manager is leading a project of gaming equipment development. The project team holds a monthly status review meeting with the product owner to review post-iteration deliverables. What’s the best communication type to use in a status review meeting?

Question Title

* 15. To see where each team member stands regarding a certain decision, a project manager uses the Fist of five voting technique. When the team starts voting, one member holds up five fingers. What does it mean?