Best of Luck!

Question Title

* 1. During product validation, a key stakeholder refuses to sign off the acceptance document, claiming that some of the functionalities do not meet their expectations. What should the project manager have done to avoid this situation?

Question Title

* 2. After being assigned by management to lead a new project, the project manager is immediately asked to develop the project charter in order to launch the project as soon as possible. To develop the project charter, the project manager will need the following documents: (Select three)

Question Title

* 3. A project manager is assigned to a project consisting of four phases. Which of the following meetings should the project manager hold at each phase to ensure the continuous commitment of project stakeholders?

Question Title

* 4. While managing an industrial project, a project manager notices that two stakeholders are always debating which may have a negative impact on the project. Which of the following options is used to document and monitor this type of situation?

Question Title

* 5. A project manager notices that his colleague, who is a fellow project manager, shows up at the office with new high-tech gadgets every day. This raises his suspicions that his colleague might be accepting gifts from hardware vendors who will be bidding on one of their company’s upcoming multimillion-dollar contracts. Which of the following should the project manager do?

Question Title

* 6. Constraints and assumptions are important for projects. They should be identified, controlled, and monitored continuously. Wrong assumptions or constraints can impact the project. For instance, when a constraint turns out to be wrong, it affects the project:

Question Title

* 7. When the execution of a rebranding project was completed, several key stakeholders, including the sponsor, were reluctant to accept deliverables and close the project. What should the project manager do in this situation? (Select three)

Question Title

* 8. All of the following statements are true, except:

Question Title

* 9. A project manager is leading a hotel construction project in a foreign country where corruption is widely spread. After facing trouble obtaining the required construction permits from local authorities, a team member suggested giving a bribe to the local officials to get things going and execute the project without issues. How should the project manager react?

Question Title

* 10. A project manager is working on a contract. Now that they completed their contract and closed the project, the project manager is out of work. What type of organizational structure does the project manager work in?

Question Title

* 11. You are simultaneously managing six projects in the company. Two projects are of a similar type, while the other four are entirely different. You work as a ______________.

Question Title

* 12. During the kick-off meeting of their first project, the project manager presents the project plan to the attending stakeholders. When going through the details, the project manager notices that most stakeholders don’t seem happy about the plan. A certain stakeholder even expressed their frustration with how inaccurate this plan describes their expectations. What is the most likely reason behind the project manager’s inaccurate description of stakeholders’ requirements?

Question Title

* 13. A project manager was assigned to a park redevelopment project which consists of cleaning and equipping the park for local families and residents. The project involves a really big number of stakeholders since it includes multiple phases and different types of tasks to execute. What should the project manager do?

Question Title

* 14. During the planning phase, the project manager speculated that there will be no changes in the composition of the project steering committee. But, since any change could be very critical to the project, the project manager assigned a team member to monitor for triggers. Where should the name of the person responsible for monitoring the steering committee be recorded?

Question Title

* 15. Halfway through the project, the sponsor designates an inspector to check the quality of the deliverables so far. The project manager doesn’t know the inspector in person, but they overheard that they are not flexible and working with them is usually hard. What is the best way for them to handle the situation?