NEC People State of the Industry Survey

Please answer these questions (where relevant) as to your general experience of your recent and current projects being managed under NEC contracts.
1.About You:
2.Which of the following best describes the company or role you typically represent:
3.How many of your projects use an online administration tool to manage your NEC documentation flow?
0%
100%
4.Where a cloud-based system is used between Client/Contractor, what proportion of subcontract packages are also managed under a cloud based system?
0
100%
5.As a percentage, approximately what proportion of your early warnings would you say go on to become compensation events?
0
100%
6.Sometimes early warnings can be viewed as a commercial tool by either party which is not their intent. As a percentage, how often do you see early warnings being taken negatively?
0
100%
7.Is there a common Z clause you keep seeing that you do not consider particularly helpful?
8.What percentage of Z clauses would you consider are worthy, useful and contribute to making a positive difference to the management of that project?
0
100%
9.Do you have an example of what you thought was a crazy Z clause?
10.How often do you typically get an Accepted Programme?
11.Have you ever experienced a deemed accepted programme where the Project Manager/Service Manager had failed to respond to the programme and a subsequent reminder?
12.What is the average response time would you say it takes for the relevant party to respond to a CE quotation?
13.What percentage of quotations do you find a Project Manager (ECC) or Service Manager (PSC) give a Project Manager/Service Manager assumption?
0
100%
14.What percentage of CE quotes would you say typically have a specific programme attached to it?
0
100%
15.Have you ever experienced a deemed accepted for compensation event quotations, where the Project Manager/Service Manager had failed to respond to the quotations and a subsequent reminder?
16.What would you say is the average time for a CE that is notified to become implemented (agreed)?
17.How subjective do you find assessing compensation events under 60.1(12) for unforeseen physical/ground conditions to be?
18.How subjective do you find assessing compensation events under 60.1(13) in excess of 1 in 10 year weather events?
19.What percentage of people in your experience do you find being contractual IS considered bad or negative?
0
100%
20.Do you ever find that having a good relationship leads to relaxing of following the contractual rules?
21.Do you find that with CE’s there is still a tendency to wait and see what the actual cost was before agreeing the value of a compensation event?
22.On what percentage of new contracts do you undertake joint contract training between the key parties for a particular project?
0
100%
23.Roughly what percentage of subcontracts let by the Contractor on your ECC contracts are carried our using the Engineering and Construction Subcontract or the Engineering and Construction SHORT Subcontract (i.e. back to back with an NEC contract)?
0
100%